In the summer of 2012, Schrimpf Landscaping partnered with SINE WALL to create a large pump station with tall walls and various backfill conditions on a tight schedule for the Army Corp of Engineers.


CONTRACTOR

INFRASTRUCTURE OWNER

CHALLENGES

Accelerated construction schedule, tall walls, long reinforcement, multiple backfill types.

RESULT

Schrimpf Landscaping and SINE WALL delivered a project with high quality, functional walls built on time for the Army Corp of Engineers. These +50’ tall walls were completed with SINEstrip soil reinforcements greater than 50’ in length. The highly aggressive construction schedule demanded dedication and perfection from the general contractor, the wall builder, and SINE WALL’s supply chain.